Principal Contractor WHS Management Plan Builder
Check whether your construction project needs a WHS management plan, then build one covering the reg 309(2) content areas — names and WHS responsibilities, consultation and issue resolution, site safety rules, and SWMS arrangements.
Last verified: 21 June 2026For more work health and safety tools and guides, see the Safety Hub. If you are doing high risk construction work, also check whether you need a Safe Work Method Statement.
Step 1 — Do you need a WHS management plan?
A WHS management plan is required when the work is a construction project. Under the model WHS Regulations, a construction project is construction work costing $250,000 or more (reg 292). Victoria uses $350,000 under its separate OHS regime.
New South Wales applies the model WHS Regulations. A construction project is construction work costing $250,000 or more (reg 292). Western Australia mirrors the model laws. Confirm your obligations with your WHS regulator.
Step 2 — Project and party details
These appear at the top of your WHS management plan.
Step 3 — Plan content (reg 309(2))
Reg 309(2) sets out the four areas a WHS management plan must cover. The text below is a general starting point — tailor it to your actual project, parties and site before relying on it.
The plan opens below. Use Print / Save as PDF to produce a clean printable copy.
Get notified when rates change
Free alerts when minimum wage, award rates, or workplace laws are updated.
Free forever. No spam. Unsubscribe anytime.
General information and estimates only — not legal, financial or tax advice. Always check your specific award, agreement or contract, or a qualified professional, before you rely on the result.